Try These SAP C_TPLM22_64 Exam Questions – Updated 2018

Free demo of SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 certification exam is available before the real C_TPLM22_64 exam purchase once you are sure about the C_TPLM22_64 exam purchase then make the payment and get the SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam dumps practice software instantly. PDF Questions and Answers booklet with the SAP C_TPLM22_64 exam practice software is also available with an attractive offer of 30% discount. The booklet and practice test software together facilitates you for learning and practice both in the best manner. The most updated SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam questions of SAP C_TPLM22_64 exam are provided in the PDF booklet.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:

A. The control key is set to no scheduling.
B. The scheduling type is set to capacity requirements only.
C. The normal duration of each activity is missing.
D. There is a loop in the network.

Answer: B

Question: 22

What does ‘E’ determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?
Please choose the correct answer.
Response:

A. E determines that the sales order is a controlling object
B. E determines that the sales order is a project is a controlling object
C. E determines that the sales order items are relevant for delivery through sales and distribution
D. E determines that the sales order is a cost object

Answer: D

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD

New Updated C_TPLM22_64 Exam Questions C_TPLM22_64 PDF dumps C_TPLM22_64 practice exam dumps: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html